Summary

This rule tests the completion status of each net that falls under the scope (full query) of the rule. If a net is incomplete then each completed section (sub-net) is listed along with the routing completion. The routing completion is defined as:

(connections complete / total number of connections) x 100

Constraints

None

How Duplicate Rule Contentions are Resolved

All rules are resolved by the priority setting. The system goes through the rules from highest to lowest priority and picks the first one whose scope expression matches the object(s) being checked.

Rule Application

Batch DRC.

Tips

  1. Some split plane DRC checks require the Un-Routed Net rule to be Batch-enabled for them to work.

 