Placement - Permitted Layers

 

Rule category: Placement

Rule classification: Unary

Summary

This rule specifies which layers components can be placed on, during placement with the Cluster Placer.

Constraints

Default constraints for the Permitted Layers rule.

  • Permitted Layers– the layers permitted to be used by the Cluster Placer during autoplacement. The following layer options are available:
    • Top Layer – allow component placement on the top layer.
    • Bottom Layer – allow component placement on the bottom layer.

How Duplicate Rule Contentions are Resolved

All rules are resolved by the priority setting. The system goes through the rules from highest to lowest priority and picks the first one whose scope expression matches the object(s) being checked.

Rule Application

During autoplacement with the Cluster Placer.

Tips

  1. The Cluster Placer does not change the layer a component is on – you must set the component layer prior to running the placer.

 

Note

This documentation page contains information for an older version of Altium Designer. The latest, online documentation can be found here.